La Tiên Villa Nha Trang Construction Progress – November 2026
-
1
La Tiên Villa progress, week 2 of November 2026: 240 villas under construction
- 1. 1 66 villas on lots BT19.04, BT19.09, BT19.10, BT19.14, BT19.15: shell almost complete
- 1. 2 60 villas of Type 3A and Type 3B: concrete floor slabs in progress
- 1. 3 62 villas on lots BT19.20 to BT19.26: structure rising to the second and third floors
- 1. 4 52 villas on lots BT19.13, BT19.16, BT19.17, BT19.18: foundation stage
- 2 What comes next for La Tiên Villa
- 3 Frequently asked questions about La Tiên Villa progress
La Tiên Villa construction progress continued to pick up pace in November 2026. La Tiên Villa Nha Trang is the low-rise villa zone of the Vega City Nha Trang urban area, where several contractors are now building in parallel across the BT19 lots. This article summarises the latest figures from the week 2, November 2026 progress report, with real photos from the site, so that anyone interested in La Tiên Villa Nha Trang villas can see exactly where the project stands.

Aerial view of the La Tiên Villa zone, from the week 2, November 2026 progress report.
La Tiên Villa progress, week 2 of November 2026: 240 villas under construction
According to the week 2, November 2026 progress report, four construction teams are working on 240 villas across the BT19 lots. The villas that started first are close to finishing their shell and are now on walls and exterior plastering, while the newest villas are at the foundation and ground-floor slab stage.
66 villas on lots BT19.04, BT19.09, BT19.10, BT19.14, BT19.15: shell almost complete
The group of 66 villas built by contractor Việt Anh is the furthest ahead. All 66/66 villas have completed their foundations, and 60/66 (91%) have finished the main structure. Walls and exterior plastering are done on 48/66 villas, or 72%. Along the internal roads, rows of three-storey villas have clearly taken shape and many have already had their scaffolding removed.

A row of La Tiên Villa villas with walls and exterior plastering done, photo taken 6 November 2026.

Villas finishing their main structure, covered with safety netting and scaffolding (6 November 2026).
60 villas of Type 3A and Type 3B: concrete floor slabs in progress
Contractor Viteccons is building two villa types. For Type 3A, 20 villas on lots BT19.7 and BT19.8, the first-floor slab is done on 16/20 villas (80%), the second-floor slab on 14/20 (70%), and the third-floor and roof slabs on 8/20 (40%). That means 8 Type 3A villas already have their full frame up to the roof.

Workers on the third-floor slab of a Type 3A villa (5 November 2026).

A Type 3A villa with its roof slab poured, with the Vega City Nha Trang towers behind (3 November 2026).
Type 3B covers 40 villas on lots BT19.5, BT19.6, BT19.11 and BT19.12. The first-floor slab is poured on 28/40 villas (70%), the second-floor slab on 16/40 (40%) and the third-floor slab on 4/40 (10%).

Type 3B villas during slab works, with scaffolding across the façade (3 November 2026).
62 villas on lots BT19.20 to BT19.26: structure rising to the second and third floors
Contractor VELA is responsible for 62 villas on seven lots from BT19.20 to BT19.26. Foundations are complete on 46/62 villas (about 74%), the second-floor structure on 26/62 (about 42%) and the third-floor structure on 18/62 (about 29%).

Villas on lots BT19.20–BT19.26 building their second and third floor structure (5 November 2026).
52 villas on lots BT19.13, BT19.16, BT19.17, BT19.18: foundation stage
For the group of 52 villas built by contractor Việt Anh, foundations are complete on 14/52 villas (27%) and the ground-floor slab on 6/52 (12%). Opening these new lots shows that the site is now building several villa groups at the same time.

Foundation works on lots BT19.13–BT19.18, with a Vega City tower behind (6 November 2026).

Pouring the ground-floor slab on newly started villas (6 November 2026).
Based on the week 2, November 2026 figures, the earliest lots are moving on to walls, exterior plastering and façade finishing. The Type 3A and 3B lots and lots BT19.20–BT19.26 are pouring the upper floor slabs, while the 52 villas on lots BT19.13–BT19.18 have just started their foundations. Zoom Apartment will keep updating La Tiên Villa progress as new reports come in. You can also read our previous La Tiên Villa progress update.
Frequently asked questions about La Tiên Villa progress
Where is La Tiên Villa Nha Trang?
La Tiên Villa is the villa zone of the Vega City Nha Trang urban area, in the north of Nha Trang city.
How far along is La Tiên Villa now?
According to the week 2, November 2026 report, the 66 villas on lots BT19.04–BT19.15 have finished their foundations, 91% have finished the main structure and 72% have walls and exterior plastering done. The other lots are pouring slabs from the first floor up to the roof, and the newest group of 52 villas is at the foundation stage.
How many La Tiên Villa villas are under construction?
The week 2, November 2026 report lists 240 villas under construction, split between contractors Việt Anh (66 and 52 villas), Viteccons (60 villas) and VELA (62 villas).
How can I visit La Tiên Villa in person?
Contact Zoom Apartment by hotline, Zalo or WhatsApp at +84 966 552 550 to book a site visit and receive the latest progress report.
If you are looking to buy a La Tiên Villa Nha Trang villa, see the villas for sale on our La Tiên Villa for sale page or learn more on the La Tiên Villa Nha Trang project page. The Zoom Apartment team can arrange a site visit via our hotline +84 966 552 550.
Source of figures and photos: La Tiên Villa construction progress report, week 2 of November 2026.